Wednesday, 13 February 2013

Recording of the music

                    Recording Our Music 


When the time came to add sound to our movie opening, we began by discussing the kind of sound that would fit well with our piece. Sound is key for building tension, however in our piece our climax is built more from the fast pace of the action, rather than intricate soundtrack. Therefore we decided our sound shouldn't be too complex. I played around with the keyboard settings on Garage Band, this allowed us access to a range of sounds that we could use to create our suitable musical score. Our inspiration had mainly come from musical scores using striking strings such as the theme tunes of 'Psycho' and 'Jaws'. Both pieces of music use single notes at fast tempo's to build tension. Using single, repetitive notes would prove effective in our piece, it wasn't too complex seeing as we were beginners using Garage Band. 

Our particular piece of music consisted of Orchestral Strings, repetitive C note in a low octave, that progressed to a repetitive D. We chose to change the note halfway through so that it wasn't noticeably tedious. We also increased the intensity of the track and layered another string sound when the lead male, discovers the hooded figure, as it is a climatic moment in our film opening. 


Garage Band - The recording process using the keyboard and Orchestral Strings.



By Alexandra Gibson

Tuesday, 12 February 2013

Editing

Editing Process In 10 Steps


1) We started by importing all of our footage into iMovie.
2) We ordered the raw footage into chronological order according to our storyboard.
3) We began editing the footage into order. We cropped and cut each clip to make sure that the continuity was correct, and was pleasing to watch and added a blue/green tinge colour over-lay.
4) We removed all sound from every clip as we wanted to record our own foley sounds and dialogue to get the best quality possible in our finished piece.
4) Once the footage was roughly edited together we began adding titles, including our production name and logo.
5) We began refining the footage, and cropping down clips in order to improve the fast pace of the piece.
6) We imported the foley sounds that we had recorded (See 'Foley Sound' post) and layered them over the top of our footage.
7) We then began recording our music using Garage Band (See 'Recording Our Music' post).
8) Once the soundtrack was done we recorded the separate dialogue with our actress, Lily, and layered that in sync with the footage.
9) We showed our rough cut to a group of our peers for feedback, and uploaded it to various social media sites. (See 'What Have We Learned About Technology?' post)
10) Finally we took into consideration the feedback we had from our first cut and made final improvements which included, more titling, refining clips, and adjusting sound levels.


Emili and Alexandra editing
By Alexandra Gibson

Saturday, 9 February 2013

Foley Sound Recording


Foley Sound Experiment
We decided that the wind on our footage was too harsh, therefore we needed to rerecord some natural outdoor noise including slight wind, birds ect in order to fill in the gaps with no dialogue. As we stripped all clips of their sound, we needed to film Foley sounds that sounded like swings, as well as rerecord our actress’s dialogue. Here is a video montage of the Foley sounds that we recorded:

We intend on using the sounds we recorded in our film opening.

By Emili Hone and Alexandra Gibson



 

Bringing Flick Trick Productions to the social media

Connecting to our Audience

We decided to make a Facebook page and Twitter account for Flick Trick Productions to increase its publicity and to connect to our audience






FACEBOOK
By making ourselves available to our audience we can get feedback and support on our opening. We then know what they audience like about our opening and what they think could be improved on.
We can also see who appreciates our work in general
 






TWITTER



Twitter helps to get our opening noticed and publicised. People then make comments and some suggest how to improve the opening.

Monday, 4 February 2013

The day we filmed

The day we filmed our Horror Opening

We arrived at our chosen destination to film our horror opening, this was a park close to Emili and seemed suitable for what we wanted to achieve. It had a playground, a set of football pitches and most importantly some woods beside it. Luckily within the woods there was a hollow tree which we decided to use as the hiding spot for our character jack. The weather was perfect, cloudy and almost gloomy; the only downside was that it was freezing.
It took us about 3 hours to film until we were content with the footage. We took turns to film and had agreed before hand who would do what scene by writing the name of the chosen one next to the storyboard pictures. We filmed everything at least 3 times over and did shots in different positions so we'd have a good amount to choose from when it came to editing.

After we finished filming the main shots we took some short clips of things such as the swings and a gate into the playground. These came useful later on when it came to editing because we could put them in-between shots to break up them up, also adding much need tension to the final opening.

Sunday, 3 February 2013

Pictures from the day of production

Here are some of the pictures that we have taken while we were filming the film opening to show the equipment that we have used and the process of the filming day.


Filming the first shot of the horror film opening



Using a crane to create the effect that we wanted just before Lily says number '10'

By Melissa Owen, Alexandra Gibson, Emili Hone and Harry Crotty


Saturday, 2 February 2013


Detailed Editing Schedule


We often have free periods together as well as lessons to edit (although not all of the lessons will be available for editing). I will add particular events onto our editing schedule as and when we do them. Below are all the opportunities that we have to edit after we film on the 3rd February, until our first draft deadline set by our teacher on the 1st March:




Date and time available to edit

Anything that we got done

Monday 4th February between 10:10am and 11:15am


All footage uploaded to the computer and imported into imovie. We ordered all the footage in the order of our storyboard.

Wednesday 6th February between 10:10am and 11:15am


We slightly re-ordered the footage so that it did not completely follow the original storyboard as we thought that it fitted better.

Thursday 7th February between 11:30am and 12:30pm AND 14:30pm and and 15:40pm


Cutting clips.

Friday 8th February between 11:30am and 12:30pm


Cutting clips. We also took all sound off as we realised the wind was too loud. We decided that we would need to add the sound separately, which means re-recording our actress’s dialogue.

Monday 11th February between 10:10am and 11:15am


Edited saturation and added a blue tinge to the clips to add a ‘creepy’ feel.

Tuesday 12th February between 11:30am and 12:30pm



Wednesday 13th February between 13:30pm and 14:30pm


Emili and Sasha went to a park to film white noise for the background as well as monotone sounds by banging the slide. We also recorded foley sound for the swing by rattling a chain against a fence.

Friday 15th between 14:30pm and 15:40pm


HALF TERM WEEK WHERE WE ARE UNABLE TO EDIT AS ALL DATA IS ON SCHOOL COMPUTERS

All sound clips taken yesterday were imported and added to the opening.

Monday 25th February between 10:10am and 11:15am

All sound clips were put into place on the opening and the opening was complete for the first screening on the 1st March. 
Wednesday 27th February between 10:10am and 11:15am



Thursday 28th February between 11:30am and 12:30pm AND 14:30pm and and 15:40pm


by Emili Hone